Dear reader, We need your support to keep the flame of knowledge burning bright! Our hosting server bill is due on June 1st, and without your help, Bharatpedia faces the risk of shutdown. We've come a long way together in exploring and celebrating our rich heritage. Now, let's unite to ensure Bharatpedia continues to be a beacon of knowledge for generations to come. Every contribution, big or small, makes a difference. Together, let's preserve and share the essence of Bharat.

Thank you for being part of the Bharatpedia family!
Please scan the QR code on the right click here to donate.

0%

   

transparency: ₹0 raised out of ₹100,000 (0 supporter)


Mumbai Metro Pink Line 6
Maha Mumbai Metro.png
Overview
StatusLine 6 (under construction)
OwnerMMRDA
Line number6
LocaleWestern Suburbs, Mumbai
TerminiLokhandwala
Kanjurmarg
Stations13
WebsiteLine 6
Service
TypeRapid Transit
SystemMumbai Metro
History
Commenced2017; 7 years ago (2017)
Planned opening2022; 2 years ago (2022)
Technical
Line length14.47 km (8.99 mi)
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Route map
Template:MM Line 6

Pink Line 6 of the Mumbai Metro, or the Swami Samarth Nagar-Jogeshwari-Vikhroli-Kanjurmarg Line, is part of the metro system for the city of Mumbai, India. This line is fully elevated.

Plans[edit]

The 14.47 km long Lokhandwala-Jogeshwari-Vikhroli-Kanjurmarg (Pink Line) is to have 13 stations and cost Rs. 6,672 crore. It is to be an elevated corridor.

It is to connect Swami Samarth Nagar-Lokhandwala in Andheri in the western suburbs to Vikhroli and Kanjurmarg in the eastern suburbs. The stations include Lokhandwala Complex, Adarsh Nagar, Momin Nagar, Jogeshwari-Vikhorli Link Road, Shyam Nagar, Mahakali Caves, SEEPZ Village, Saki Vihar Road, Ram Baug, Powai Lake, IIT Powai, Kanjurmarg (W) and Vikhroli - Eastern Express Highway. Pink Line is to provide interchange with Yellow Line at Adarsh Nagar, with Aqua Line at SEEPZ, with Green Line at Kanjurmarg (West), with Red Line at Jogeshwari Vikhroli Link Road and the Mumbai Suburban Railway at Jogeshwari on Western Railways and Kanjurmarg on Central Railway. Construction is to begin by December 2018.[1] [2] It is to be ready by 2021–22.[3]

Construction[edit]

The line was approved by Chief Minister Fadnavis on 19 October 2016. The MMRDA issued a tender to conduct a detailed aerial mapping survey of the alignment in April 2017. Authorities were to determine the location of trees along the alignment with an accuracy of up to 10 cm, utilizing a differential GPS (DGPS), while a digital aerial triangulation system is to help determine the types of trees, their heights and diameters.[4]

Current status[edit]

Sr. No. Name of Work Description Status as of[5]
21 May 2019 July 2019 Sep 2019 Oct 2019 Nov 2019 Dec 2019 Jan 2020 07 Sep 2020 01 Nov 2020 01 Mar 2021
1 Soil Investigation Works soil investigation work for pier foundation completed 39.4% 45.1% 58% 70.66% 73.84% 80.79% 82.18% 83.26% 85.82% 94.18%
2 Utility Works Works completed 25.2% 30.0% 36.6% 49.53% 53.01% 56.17% 56.45% 56.70% 59.58% 65.14%
3 Piling Works piling work for foundations completed 7.8%% 9.9% 14.10% 18.32% 23.64% 30.25% 33.37% 45.55% 48.36% 59.01%
4 Pile Cap Works Pile Cap work completed 0.5% 0.9% 2.05% 4.16% 6.71% 11.63% 14.75% 28.28% 34.32% 48.62
5 Pier Works Pier work completed 0.52 2.14% 3.35% 5.67% 7.03% 19.79% 24.42% 37.12%
6 Station Work Work is in progress at all the 13 stations Swami Samarth Nagar, Adarsh Nagar,Jogeshwari (West), Jogeshwari-Vikhroli Link Road, Shyam Nagar,Mahakali Caves, SEEPZ Village, Saki Vihar Road, Rambaug, Powai Lake, IIT Powai, Kanjurmarg (West), Vikhroli (EEH) 15.82% 18.00%

Stations[edit]

The line will consist of 13 stations starting from Swami Samarth Nagar in Lokhandwala Complex, Andheri (West) to Vikhroli (East). It will have interchanges with Lines 2, 7, 3 and 4.[6]

Pink Line 6
# Station Name Status Interstation Distance Connections Layout
English Marathi
1 Swami Samarth Nagar (Lokhandwala) स्वामी समर्थ नगर (लोखंडवाला) Under Construction 0 km (0 mi) None Elevated
2 Adarsh Nagar आदर्श नगर Under Construction 0.7288 km (0.4529 mi)  Yellow Line 2  (Under Construction) Elevated
3 Jogeshwari (West) जोगेश्वरी (पश्चिम) Under Construction 0.9891 km (0.6146 mi) Jogeshwari railway station,
Western Line (Mumbai Suburban Railway)
Elevated
4 JVLR Junction जेवीएलआर जंक्शन Under Construction 1.598 km (0.993 mi)  Red Line 7  (Under Construction) Elevated
5 Shyam Nagar श्याम नगर Under Construction 0.9619 km (0.5977 mi) None Elevated
6 Mahakali Caves महाकाली लेणी Under Construction 1.5478 km (0.9618 mi) None Elevated
7 SEEPZ Village सीप्झ गाव Under Construction 1.1228 km (0.6977 mi)  Aqua Line 3  (Under Construction) Elevated
8 Saki Vihar Road साकी विहार रोड Under Construction 1.1363 km (0.7061 mi) None Elevated
9 Rambaug (Powai) रामबाग (पवई) Under Construction 1.0122 km (0.6290 mi) None Elevated
10 Powai Lake पवई तलाव Under Construction 0.8493 km (0.5277 mi) None Elevated
11 IIT Powai आयआयटी पवई Under Construction 1.0644 km (0.6614 mi) None Elevated
12 Kanjurmarg (West) कांजूरमार्ग (पश्चिम) Under Construction 1.658 km (1.030 mi)  Green Line 4  (Under Construction),
Kanjurmarg railway station,
Central Line (Mumbai Suburban Railway)
Elevated
13 Vikhroli EEH विक्रोली इइएच Under Construction 1.056 km (0.656 mi) None Elevated

References[edit]

  1. "Work on Mumbai's Metro-6 corridor to kick off by December". hindustantimes.com. Retrieved 13 August 2018.
  2. "Mumbai: MMRDA plans to begin work on five more Metro lines by December". The Indian Express. 7 April 2017. Retrieved 7 April 2017.
  3. "Mumbai's east-west connectivity to get a boost with another Metro corridor". hindustantimes.com. 2 March 2017. Retrieved 2 March 2017.
  4. "MMRDA to begin tree count for Metro 6". mid-day. Retrieved 6 April 2017.
  5. https://mmrda.maharashtra.gov.in/its#
  6. "DPR for Line 6". MMRDA.